Project - Manhole / Pumping Station Tank Repair
NCS utilised Xypex Megamix II and Epigin to reline an effluent pumping station tank, which was badly damaged from hydrogen sulphide attack. The manhole measures 6 metres in circumference, 6 metres deep and was successfully reinstated by NCS.
The task was to reline the underground tank which was badly damaged from hydrogen sulphide attack. As the tank is part of a two stage pumping system NCS could not close down the system for any length of time. NCS decided to design and install a run dry bypass system built within the tank it self.
This saved the client significant amount of time and achieved project cost savings.
Effluent flows : 35,000 ltrs per hour
Inlets : 1 x 150mm inlet 800mm above tank base
1 x 100mm inlet 1200mm above tank base
1 x 80mm pressure line 4 meters above tank base
1 x 225 balance line 400mm above tank base |

|